Monitoring Program Data View Archives
Environmental monitoring of surface water (turbidity), air (dust and mercury vapor), and noise was conducted in accordance with the CMI work plan during the removal phases of the remediation program. Chemours is committed to sharing monitoring data (turbidity, dust, mercury vapor) collected during remedy implementation with the community. The graphs below contain data from the various monitoring locations around the project area.1. Wind Monitoring
Click Image to Enlarge
2. PM10 Particulate (Dust) Monitoring
Click Image to Enlarge
3. Mercury Vapor Monitoring
Click Image to Enlarge
4. Turbidity Monitoring
Click Image to Enlarge
Comments
The upstream monitoring station (LAB) stopped transmitting data at approximately 1415. An evaluation of the station will occur on Tuesday, July 11th to further assess this issue.
Operating issues were identified at downstream monitoring station SW-9 and will also be further assessed on July 11th. As such, turbidity data from station ADJ-ABD was plotted for the downstream measurements recorded on Monday, July 10th.
View Archives