Environmental monitoring of surface water (turbidity), air (dust and mercury vapor), and noise was conducted in accordance with the CMI work plan during the removal phases of the remediation program. Chemours is committed to sharing monitoring data (turbidity, dust, mercury vapor) collected during remedy implementation with the community. The graphs below contain data from the various monitoring locations around the project area.1. Wind Monitoring
Click Image to Enlarge
2. PM10 Particulate (Dust) Monitoring
Click Image to Enlarge
Comments
The elevated dust measurement at monitoring station AM-2 between approximately 1200 and 1230 is attributed to personnel activities near the site trailer during lunch. There were no site-related remediation activities ongoing at the time.
3. Mercury Vapor Monitoring
Click Image to Enlarge
4. Turbidity Monitoring
Click Image to Enlarge
Comments
The upstream monitoring buoy and associated turbidity meter was taken out of service at approximately 1100.