Environmental Monitoring 12/15/17

USEPA issued a modification to the Pompton Lakes Works facility RCRA permit on June 22, 2015 to remove mercury impacted soils and sediment from Pompton Lake. The remedy encompasses four areas consisting of approximately 40 acres. The areas identified in the permit modification include upland soils between Rotary Park and the lake, the lake bottom adjacent to Rotary Park, and the lake bottom at two downstream locations. A map depicting these areas is provided above. A Corrective Measures Implementation (CMI) work plan which describes the means and methods upon which the remedy will be completed was approved by USEPA on April 22, 2016. Field activities associated with the remedy commenced in early June 2016.  Work completed in 2016 consisted of the removal of soils in the Uplands Area and sediments in the Island Area and Lake Area A.  Work completed in 2017 consisted of the removal of sediment from the Delta Area. Environmental monitoring of surface water (turbidity), air (dust and mercury vapor), and noise is being conducted in accordance with the CMI work plan during the removal phases of the remediation program. Download Monitor and Removal Area Detail View Work to be completed in 2018 consists of the placement of eco-layer material in the Delta Area and Island Area as well as restoration in these two areas. As of 8 July 2018, eco-layer material placement in both areas has been completed and restoration is in progress.

Monitoring Program Data View Archives

Chemours is committed to sharing monitoring data (turbidity, dust, mercury vapor) collected during remedy implementation with the community. The graphs below contain data from the various monitoring locations around the project area.

1. Wind Monitoring

Wind Environmental Monitor Graph
Click Image to Enlarge

Comments

NOTE:  Due to the snow on Thursday, December 14, 2017 and the lack of any sediment operations, the wind meter was not set up to collect data.  The only activity that took place on this day was demobilization of large-scale equipment.


2. PM10 Particulate (Dust) Monitoring

Dust Environmental Monitor Graph
Click Image to Enlarge

Comments

NOTE:  Due to the snow on Thursday, December 14, 2017 and the lack of any sediment operations, the dust meters were not set up to collect data.  The only activity that took place on this day was demobilization of large-scale equipment.


3. Mercury Vapor Monitoring

Mercury Environmental Monitor Graph
Click Image to Enlarge

Comments

NOTE:  Due to the snow on Thursday, December 14, 2017 and the lack of any sediment operations, the mercury vapor meter was not set up to collect data.  The only activity that took place on this day was demobilization of large-scale equipment.


4. Turbidity Monitoring

Turbidity Environmental Monitor Graph
Click Image to Enlarge

Comments

NOTE:  No water work took place on Thursday, December 14, 2017.  As such, the turbidity meters were not set up to collect data.  The only activity that took place on this day was demobilization of large-scale equipment.


View Archives